| | Mon Jun 25, 2012 Bayfield Rainy River Drilling Update, NW Ontario Publisher: Don Myers: Director Author: Bob Marvin, P.Geo, CPG, VP of Exploration & Qualified Person
|
| | Rainy River Eastern Burns Block Exploration:
Drill Hole RR12-18 was completed to 680 metres after intercepting main zone.
The rig has been moved to the next collar location to begin hole RR12-19, in-between holes RR12-5 and RR12-3.
Bob Marvin, P.Geo., CPG, VP of Exploration is the Qualified Person as defined by NI 43-101 and has provided and approved the drilling updates that are posted here. |
| |
| | You can view the Previous Update from the Field item: Tue Jun 26, 2012, Bayfield Rainy River Drilling Update, NW Ontario
You can view the Next Update from the Field item: Fri Jun 22, 2012, Bayfield Rainy River Drilling Update, NW Ontario